A
comparison of alternative and conventional infrastructure costs
on a 6.6 acre site in Surrey,BC.
Infrastructure Cost |
Conventional |
Alternative |
boulevarde
landscaping
storm sewer
water mains
water tie-in
connections
lot grading/swales
boulevarde
tree planting |
$30,000
$205,820
$113,705
$18,177
$24,450
$20,000
|
$48,987
N/A
$191,627
$58,521
$24,420
$35,598
|
Total
Infrastructure Costs
entire site |
$964,354
|
$1,093,340
|
Total
Per Dwelling Unit Cost |
$23,520
|
$4,408
|
|
|
|
|